Event Plan Review Timeline

The review, day by day

Artist’s rendering

Below is a detailed overview of The Mill Group’s efforts to receive approval from the Village of Vicksburg for its Event Plan for the 2027 Summer Concert Series. The Development Agreement that governs the process calls for a 90-day review window. The Village set a 66-day window. On day 129, November 23, the Vicksburg Planning Commission voted to table its recommendation.

Day counts run from our July 17, 2026 submission · Updated November 24, 2026

The review, by the numbers

A 66-day schedule. A 90-day limit. 129 days and counting.

66 Days

The Village’s own schedule, July 17 to a September 21 vote

90 Days

The review period in the Development Agreement, ending October 15

118 Days

Until our first meeting with the Village’s planner and engineers

129 Days

When the Planning Commission tabled the plan, November 23

Response times

Who was waiting on whom

How long each side waited for a response from the other.

The Mill GroupThe Village

The Mill Group

Event Plan submitted

July 17

76 days

Waiting on the Village

The Village

First written comments from the Village’s planner

Oct. 1

The Mill Group

Our request for a joint meeting

Oct. 7

36 days

Waiting on the Village

The Village

First meeting with the Village’s reviewers

Nov. 12

The Mill Group

Our full response

Oct. 7

23 days

Waiting on the Village

The Village

The planner’s second review

Oct. 30

The Village

Planner’s first comments

Oct. 1

6 days

Mill Group turnaround

The Mill Group

Our full response

Oct. 7

The Village

First meeting with the reviewers

Nov. 12

4 days

Mill Group turnaround

The Mill Group

Final Event Plan

Nov. 16

The Village

Site plan agreed

Sept. 21

2 days

Mill Group turnaround

The Mill Group

Site plan filed

Sept. 23

The full timeline of events

The Mill GroupThe Village

  1. May–June 2026

    We ask for a faster review, and offer help

    We meet with groups of Council members, Village staff and the Village’s attorney. We explain that artists book their next summer’s shows in September and October and ask for a review faster than 90 days. We offer to make our experts available to the Village, or to pay for the Village to hire its own independent event consultant.

  2. June 12

    The Village sets the schedule

    The Village’s attorney puts the dates in writing: Event Plan by July 17, Council vote September 21.

  3. July 17 · Day 0

    Event Plan submitted, on schedule

    Prepared by Metropolis, Gensler, Fortified and our production team.

  4. Aug. 21 · Day 35

    A new standard of review

    The Village’s attorney suggests the Agreement’s review standard contains a “typo” and that a different zoning standard applies. It was not a typo, and we walk Village staff through why. The same letter confirms the concert-venue use is already permitted.

  5. Sept. 10 · Day 55

    First request for a site plan

    The Village’s attorney asks, for the first time, for a site plan for the temporary event areas.

  6. Sept. 21 · Day 66

    The Village’s own vote date passes

    No vote is taken. We agree to file a site plan while reserving our position that the Agreement does not require one. The Village Manager tells us plans without a building do not normally go to the Village’s engineers.

  7. Sept. 23 · Day 68

    Site plan filed

    Seven pages, with no new buildings. We offer to have our team meet with Planning Commission and Council members.

  8. Oct. 1 · Day 76

    First written comments from the Village’s planner

    A 44-item checklist for permanent development under a zoning ordinance adopted in March 2026. About 40 of the items do not apply to temporary events or were already answered in our submissions.

  9. Oct. 6 · Day 81

    First comments from the Village’s engineers

    They review only the one-page site plan and ask for traffic, emergency and sanitation plans that were already in the July 17 Event Plan.

  10. Oct. 7 · Day 82

    We answer, and send the plan to the engineers ourselves

    Full response to both reviewers, with the Event Plan sent directly to the engineers. We ask for a joint meeting with the reviewers, and ask again on October 12.

  11. Oct. 15 · Day 90

    The Agreement’s 90-day review period ends

    No recommendation, no vote and no meeting with the reviewers.

  12. Oct. 30 · Day 105

    First request for environmental records

    The Village’s attorney calls them “critical.” The Village approved the site’s Brownfield Plan in 2019, and it is posted on the Village’s own website. Environmental cleanup is overseen by the state agency, EGLE. The same letter forwards the planner’s second review, which calls for paving, landscaping and a traffic study for temporary concerts.

  13. Nov. 2 · Day 108

    A resolution against school grass parking

    At our Council presentation, the Council passes a resolution asking the School Board not to allow concert parking on three grass areas at the schools. School parking had been in the plan since July 17. We move all parking onto Mill property.

  14. Nov. 5 · Day 111

    Planning Commission moved

    The November 9 Planning Commission meeting is postponed to November 23. Under the schedule the Village’s attorney confirms in writing, staff would finish their final review by November 16.

  15. Nov. 12 · Day 118

    First meeting with the Village’s planner and engineers

    After requests since early October, our experts finally sit down with the Village’s reviewers, 28 days after the 90-day period ended. The reviewers press for a traffic study and treat four temporary concerts as permanent development.

  16. Nov. 16 · Day 122

    Final Event Plan submitted

    The Event Plan for Small Events, with all parking on Mill property. The staff review scheduled for this date is not completed.

  17. Nov. 19 · Day 125

    Final plan updated

    Revised in answer to the reviewers’ latest comments.

  18. Nov. 19 · Day 125

    “Has not started yet”

    That night, an attorney for the Village writes that the Agreement’s 90-day review period “has not started yet.”

  19. Nov. 20 · Day 126

    New recommendations after 5 p.m. on a Friday

    The Village’s planner recommends tabling until 12 items are addressed, including a traffic study, turn lanes, paved walkways, landscaping and lighting limits at the property line. It reaches us in the meeting packet just before 6 p.m.

  20. Nov. 23 · Day 129

    Planning Commission tables the plan

    We offer conditions to be met before the first concert. The Commission tables its recommendation.

Questions about the concerts themselves are answered in the Summer Concert Series FAQ.

Want to read the Agreement itself? See The Mill PUD Agreement, explained.