Artist’s rendering
Below is a detailed overview of The Mill Group’s efforts to receive approval from the Village of Vicksburg for its Event Plan for the 2027 Summer Concert Series. The Development Agreement that governs the process calls for a 90-day review window. The Village set a 66-day window. On day 129, November 23, the Vicksburg Planning Commission voted to table its recommendation.
Day counts run from our July 17, 2026 submission · Updated November 24, 2026
The Village’s own schedule, July 17 to a September 21 vote
The review period in the Development Agreement, ending October 15
Until our first meeting with the Village’s planner and engineers
When the Planning Commission tabled the plan, November 23
How long each side waited for a response from the other.
The Mill GroupThe Village
The Mill Group
Event Plan submitted
July 17
76 days
Waiting on the Village
The Village
First written comments from the Village’s planner
Oct. 1
The Mill Group
Our request for a joint meeting
Oct. 7
36 days
Waiting on the Village
The Village
First meeting with the Village’s reviewers
Nov. 12
The Mill Group
Our full response
Oct. 7
23 days
Waiting on the Village
The Village
The planner’s second review
Oct. 30
The Village
Planner’s first comments
Oct. 1
6 days
Mill Group turnaround
The Mill Group
Our full response
Oct. 7
The Village
First meeting with the reviewers
Nov. 12
4 days
Mill Group turnaround
The Mill Group
Final Event Plan
Nov. 16
The Village
Site plan agreed
Sept. 21
2 days
Mill Group turnaround
The Mill Group
Site plan filed
Sept. 23
The Mill GroupThe Village
May–June 2026
We ask for a faster review, and offer help
We meet with groups of Council members, Village staff and the Village’s attorney. We explain that artists book their next summer’s shows in September and October and ask for a review faster than 90 days. We offer to make our experts available to the Village, or to pay for the Village to hire its own independent event consultant.
June 12
The Village sets the schedule
The Village’s attorney puts the dates in writing: Event Plan by July 17, Council vote September 21.
July 17 · Day 0
Event Plan submitted, on schedule
Prepared by Metropolis, Gensler, Fortified and our production team.
Aug. 21 · Day 35
A new standard of review
The Village’s attorney suggests the Agreement’s review standard contains a “typo” and that a different zoning standard applies. It was not a typo, and we walk Village staff through why. The same letter confirms the concert-venue use is already permitted.
Sept. 10 · Day 55
First request for a site plan
The Village’s attorney asks, for the first time, for a site plan for the temporary event areas.
Sept. 21 · Day 66
The Village’s own vote date passes
No vote is taken. We agree to file a site plan while reserving our position that the Agreement does not require one. The Village Manager tells us plans without a building do not normally go to the Village’s engineers.
Sept. 23 · Day 68
Site plan filed
Seven pages, with no new buildings. We offer to have our team meet with Planning Commission and Council members.
Oct. 1 · Day 76
First written comments from the Village’s planner
A 44-item checklist for permanent development under a zoning ordinance adopted in March 2026. About 40 of the items do not apply to temporary events or were already answered in our submissions.
Oct. 6 · Day 81
First comments from the Village’s engineers
They review only the one-page site plan and ask for traffic, emergency and sanitation plans that were already in the July 17 Event Plan.
Oct. 7 · Day 82
We answer, and send the plan to the engineers ourselves
Full response to both reviewers, with the Event Plan sent directly to the engineers. We ask for a joint meeting with the reviewers, and ask again on October 12.
Oct. 15 · Day 90
The Agreement’s 90-day review period ends
No recommendation, no vote and no meeting with the reviewers.
Oct. 30 · Day 105
First request for environmental records
The Village’s attorney calls them “critical.” The Village approved the site’s Brownfield Plan in 2019, and it is posted on the Village’s own website. Environmental cleanup is overseen by the state agency, EGLE. The same letter forwards the planner’s second review, which calls for paving, landscaping and a traffic study for temporary concerts.
Nov. 2 · Day 108
A resolution against school grass parking
At our Council presentation, the Council passes a resolution asking the School Board not to allow concert parking on three grass areas at the schools. School parking had been in the plan since July 17. We move all parking onto Mill property.
Nov. 5 · Day 111
Planning Commission moved
The November 9 Planning Commission meeting is postponed to November 23. Under the schedule the Village’s attorney confirms in writing, staff would finish their final review by November 16.
Nov. 12 · Day 118
First meeting with the Village’s planner and engineers
After requests since early October, our experts finally sit down with the Village’s reviewers, 28 days after the 90-day period ended. The reviewers press for a traffic study and treat four temporary concerts as permanent development.
Nov. 16 · Day 122
Final Event Plan submitted
The Event Plan for Small Events, with all parking on Mill property. The staff review scheduled for this date is not completed.
Nov. 19 · Day 125
Final plan updated
Revised in answer to the reviewers’ latest comments.
Nov. 19 · Day 125
“Has not started yet”
That night, an attorney for the Village writes that the Agreement’s 90-day review period “has not started yet.”
Nov. 20 · Day 126
New recommendations after 5 p.m. on a Friday
The Village’s planner recommends tabling until 12 items are addressed, including a traffic study, turn lanes, paved walkways, landscaping and lighting limits at the property line. It reaches us in the meeting packet just before 6 p.m.
Nov. 23 · Day 129
Planning Commission tables the plan
We offer conditions to be met before the first concert. The Commission tables its recommendation.
Questions about the concerts themselves are answered in the Summer Concert Series FAQ.
Want to read the Agreement itself? See The Mill PUD Agreement, explained.